MOIXA03 | Proton Power Upgrade Project Progress and Plans at the Spallation Neutron Source in Oak Ridge Tennessee | 25 |
|
||
Funding: Work Supported by UT-Battelle, LLC, under contract DE-AC05-00OR22725 The Proton Power Upgrade project is well underway at the Spallation Neutron Source (SNS) facility in Oak Ridge, Tennessee. This project aims at increasing the proton beam power capability from 1.4 to 2.8 MW, by adding linac energy, increasing the beam current and implementing target developments to handle the increased beam power. This talk will cover the current status of increasing the beam energy, issues encountered along the way, operational experience with the new SRF cryomodules and target improvements and results from operation with beam so far. |
||
Slides MOIXA03 [3.327 MB] | ||
DOI • | reference for this paper ※ doi:10.18429/JACoW-SRF2023-MOIXA03 | |
About • | Received ※ 09 June 2023 — Revised ※ 25 June 2023 — Accepted ※ 29 June 2023 — Issue date ※ 08 July 2023 | |
Cite • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
TUPTB010 | Preservation of the High Quality Factor and Accelerating Gradient of Nb₃Sn-Coated Cavity During Pair Assembly | 405 |
|
||
Funding: This manuscript has been authored by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the U.S. Department of Energy, Office of Science, Office of High Energy Physics. Two CEBAF 5-cell accelerator cavities have been coated with Nb₃Sn film using the vapor diffusion technique. One cavity was coated in the Jefferson Lab Nb₃Sn cavity coating system, and the other in the Fermilab Nb₃Sn coating system. Both cavities were measured at 4 K and 2 K in the vertical dewar test in each lab and then assembled into a cavity pair at Jefferson Lab. Previous attempts to assemble Nb₃Sn cavities into a cavity pair degraded the superconducting properties of Nb₃Sn-coated cavities. This contribution discusses the efforts to identify and mitigate the pair assembly challenges and will present the results of the vertical tests before and after pair assembly. Notably, one of the cavities reached the highest gradient above 80 mT in the vertical test after the pair assembly. |
||
DOI • | reference for this paper ※ doi:10.18429/JACoW-SRF2023-TUPTB010 | |
About • | Received ※ 23 June 2023 — Revised ※ 28 June 2023 — Accepted ※ 02 July 2023 — Issue date ※ 09 July 2023 | |
Cite • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |