Author: Le Dréan, D.
Paper Title Page
WEPWB058 Contribution of IN2P3 to PIP-II Project: Plans and Progress 714
 
  • D. Longuevergne, N. Bippus, P. Duchesne, N. Gandolfo, D. Le Dréan, G. Mavilla, T. Pépin-Donat, S. Roset, L.M. Vogt, S. Wallon
    Université Paris-Saclay, CNRS/IN2P3, IJCLab, Orsay, France
  • P. Berrutti, J. Helsper, S. Kazakov, M. Parise, D. Passarelli, N. Solyak, A.I. Sukhanov
    Fermilab, Batavia, Illinois, USA
 
  Funding: Work supported by IN2P3. Work supported, in part, by the U.S. Department of Energy, Office of Science, Office of High Energy Physics, under U.S. DOE Contract No. DE-AC02-07CH11359.
IJCLab is one of the labs of IN2P3 (National institute of nuclear and particle physics), one of the ten research institutes composing the French National Center for Scientific Research (CNRS). Since 2018, IJCLab has been involved in the PIP-II project, assisting with the design, development, and qualification of accelerator components for the SSR2 (Single Spoke Resonator type 2) section of the superconducting linac. The first pre-production components (cavity, coupler, and tuner) have been fabricated, and some of the first qualification tests have been performed at IJCLab. This paper will summarize the complete scope of IJCLab¿s contributions to PIP-II and give updates on the performances of the first pre-production components.
 
poster icon Poster WEPWB058 [1.727 MB]  
DOI • reference for this paper ※ doi:10.18429/JACoW-SRF2023-WEPWB058  
About • Received ※ 24 June 2023 — Revised ※ 28 June 2023 — Accepted ※ 05 July 2023 — Issue date ※ 10 July 2023
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPWB137 Prototype SSR2 Tuner Procurement and Testing at IJCLab for PIP-II Project 917
 
  • N. Gandolfo, P. Duchesne, D. Le Dréan, D. Longuevergne, G. Mavilla, T. Pépin-Donat
    Université Paris-Saclay, CNRS/IN2P3, IJCLab, Orsay, France
  • M. Parise, D. Passarelli, Y.M. Pischalnikov
    Fermilab, Batavia, Illinois, USA
 
  Funding: Work supported by IN2P3. Work supported, in part, by the U.S. Department of Energy, Office of Science, Office of High Energy Physics, under U.S. DOE Contract No. DE-AC02-07CH11359.
IJCLab is involved in the PIP-II project on the design and development of accelerator components for the SSR2 (Single Spoke Resonator type 2) section of the superconducting linac. Five prototype tuners have been built and are being tested at IJCLab. After a short description of the tuner, this paper reports on the procurement strategy and the performance observed at both room and low temperatures in vertical cryostat test with SSR2 prototype cavities. This paper will also share results on accelerated lifetime tests performed in a dedicated nitrogen-cooled cryostat.
 
poster icon Poster WEPWB137 [1.395 MB]  
DOI • reference for this paper ※ doi:10.18429/JACoW-SRF2023-WEPWB137  
About • Received ※ 19 June 2023 — Revised ※ 25 June 2023 — Accepted ※ 29 June 2023 — Issue date ※ 16 July 2023
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THIAA04 Performance Analysis of Spoke Resonators, Statistics from Cavity Fabrication to Cryomodule Testing 940
 
  • A. Miyazaki, P. Duchesne, D. Le Dréan, D. Longuevergne, G. Olry
    Université Paris-Saclay, CNRS/IN2P3, IJCLab, Orsay, France
 
  Irène Joliot-Curie Laboratory (IJCLab) has been leading the development of spoke resonators in multiple interna- tional SRF projects, from fundamental R&D, prototyping, to series production. The European Spallation Source (ESS) superconducting linac is the first of its kind to put into op- eration the spoke resonators. After three prototype cavities, 29 ESS production cavities have been processed, tested, as- sembled into cryomodules at IJCLab, and then shipped to Uppsala for the site acceptance test. Seven prototypes for two other major projects, Multi-purpose hYbrid Research Reactor for High-tech Application (MYRRHA) and Proton Improvement Plan II (PIP-II), designed in collaboration with external institutions, have as well been processed and tested at IJCLab. A new challenge is to fully process series cavi- ties in industry, following the successful implementation of 1.3 GHz elliptical cavities in the other projects. This paper summarises main results obtained from fabrication to final testing, including frequency tuning strategy, performance, limitation in vertical cryostat, and identifies future direction of projects and R&D in the field of spoke cavities.  
slides icon Slides THIAA04 [4.623 MB]  
DOI • reference for this paper ※ doi:10.18429/JACoW-SRF2023-THIAA04  
About • Received ※ 18 June 2023 — Revised ※ 24 June 2023 — Accepted ※ 29 June 2023 — Issue date ※ 19 July 2023
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)